GENERAL CONSTRUCTION WORKS TO BE CARRIED OUT IN SEPTEMBER 2024

Work in progress as of early September:

Earthworks (excavation pit for Building 1) – completed;

Earthworks (excavation pit for the 2nd Building) – 20%;

The frame of the 1st floor above grade 0.000 – 90% (work is being carried out on the installation of the floor slab of the 7th floor of the first 1st section and the monolithic frame of the 6th floor of the 2nd section of building No. 1).

Masonry of walls and partitions of the 1st floor - 15% (work is being carried out on the 2nd floor of the 1st and 2nd sections)

Installation of ventilation ducts and chimneys of Building 1 – 40%;

Vertical waterproofing of the parking lot of Building 1 – 40%;