GENERAL CONSTRUCTION WORKS TO BE CARRIED OUT IN OCTOBER 2024

Work in progress as of early September:

Work on the monolithic frame of 1 house - completed;

The masonry of walls of 3-4 floors is being carried out;

Work is underway to install the roof of building 1;

Plumbing work is being carried out to lay networks;

Plastering work is being carried out on the 1st floor;

The electrical networks on the 2nd floor are being installed.