GENERAL CONSTRUCTION WORKS TO BE CARRIED OUT IN MAY 2025

House 1

  • The facade of the 1st section is being installed.

  • Installation of embedded parts for installing metal balcony railings has begun

  • Plastering work is being carried out on the basement floor.

  • Fire alarm system installation work is being completed

  • Installation of the sprinkler fire extinguishing system in the parking lot has been completed

House 2

  • Installation of a monolithic floor slab on the 6th floor

  • Masonry of walls on the 5th floor

  • Installation of sewer risers on the 5th floor

  • Installation of ventilation ducts on the 5th floor

House 3

  • Installation of a monolithic floor slab on the 6th floor

  • Masonry of walls on the 5th floor

  • Installation of sewer risers on the 5th floor

  • Installation of ventilation ducts on the 5th floor