top of page

GENERAL CONSTRUCTION WORKS TO BE CARRIED OUT IN MAY 2025
House 1
The facade of the 1st section is being installed.
Installation of embedded parts for installing metal balcony railings has begun
Plastering work is being carried out on the basement floor.
Fire alarm system installation work is being completed
Installation of the sprinkler fire extinguishing system in the parking lot has been completed
House 2
Installation of a monolithic floor slab on the 6th floor
Masonry of walls on the 5th floor
Installation of sewer risers on the 5th floor
Installation of ventilation ducts on the 5th floor
House 3
Installation of a monolithic floor slab on the 6th floor
Masonry of walls on the 5th floor
Installation of sewer risers on the 5th floor
Installation of ventilation ducts on the 5th floor
bottom of page