GENERAL CONSTRUCTION WORKS TO BE CARRIED OUT IN MAY 2024
Work being carried out as of the beginning of May:
Preparatory work – completed;
Installation of temporary roads - completed;
Tower crane installation - completed;
Installation of communication pipes under the foundation slab - completed;
Crushed stone and concrete preparation of the slab of the 1st launch complex - completed;
Monolithic frame of 1 launch complex up to grade 0.000 - 70%;
Frame structures of the 1st launch complex up to grade 0.000 - 40% (work is being carried out on the arrangement of vertical structures of section 2 of building No. 1);
Monolithic frame of 1 launch complex above grade 0.000-5%; (work is being carried out on the installation of the floor slab of the 1st floor of the first section and the floor slab of the basement floor of the 2nd section of building No. 1).