GENERAL CONSTRUCTION WORKS TO BE CARRIED OUT IN MARCH 2024

Preparatory work – 100%;

Construction of temporary roads - 100%;

Tower crane installation -100%;

Earthworks - excavation of the pit for the first launch complex is underway - 70%;

Installation of communication pipes under the foundation slab -50%;

Crushed stone and concrete preparation of the slab of the 1st launch complex - 40%;

Foundation slab 1 of the launch complex -45% (concreting of the foundation slab 1 of section 1 of building 1 has been completed);

Frame structures of the 1st launch complex up to grade 0.000 -10% (work is being carried out on the arrangement of vertical structures of section 1 of building No. 1);