GENERAL CONSTRUCTION WORK CARRIED OUT IN JUNE 2025

House 1

The facade of the 1st section is ongoing

Installation of mortgages to install metal enclosures of balconies is completed

The plastering work on the basement is completed

Work on installation of a fire alarm system

The installation of a splina fire extinguishing system in parking is completed

House 2

Completed the arrangement of monolithic slab overlapping 6th floor

Masonry walls on 6th floor

Sewaining risers are completed

The ventilation channels have been completed

House 3

Completed the arrangement of monolithic slab overlapping 6th floor

Mulching the walls of the house is completed

Sewaining risers are completed

The ventilation channels have been completed