General construction work carried out in July 2025

House 1
The facade of the 1st section is ongoing
Work on the arrangement of internal engineering networks in parking
Interior decoration work in the MZK
Work on installation of fire alarm systems has been completed
House 2
The arrangement of a monolithic slab overlapping the house is completed
Start installation of window structures
House 3
The arrangement of a monolithic slab overlapping the house is completed
The beginning of plumbing works