GENERAL CONSTRUCTION WORKS TO BE CARRIED OUT IN JANUARY 2025

Work to be done in January:

  • 1 house, 1 section:

Completion of plastering work on the 6th floor, installation of heating wiring on the 6th floor.
Completion of electrical lighting cabling for public areas (MZK) and apartments.

  • 1 house, 2 section:

Completion of masonry of internal partitions on the 5th floor and laying of sewer risers.
Completion of electrical wiring on the 1st floor.

  • 2 house:

Work is underway to install vertical structures on the 2nd floor.

  • 3rd house:

Work is underway to install vertical structures on the 2nd floor.