GENERAL CONSTRUCTION WORKS TO BE CARRIED OUT IN JANUARY 2025
Work to be done in January:
1 house, 1 section:
Completion of plastering work on the 6th floor, installation of heating wiring on the 6th floor.
Completion of electrical lighting cabling for public areas (MZK) and apartments.
1 house, 2 section:
Completion of masonry of internal partitions on the 5th floor and laying of sewer risers.
Completion of electrical wiring on the 1st floor.
2 house:
Work is underway to install vertical structures on the 2nd floor.
3rd house:
Work is underway to install vertical structures on the 2nd floor.