GENERAL CONSTRUCTION WORKS TO BE CARRIED OUT IN JANUARY 2023
Temporary water supply (well) – 100%
Dismantling of existing structures and clearing of the territory - 100%
Construction of temporary roads -100%
Preparatory work – 100% (temporary installation completed)
construction site fencing, household trailers installed,
security posts, a washing post, and construction lighting were installed
playground).
Tower crane base plate-100%
Earthworks – 30% (the excavation for the first section is being carried out)
launch complex)