GENERAL CONSTRUCTION WORKS TO BE CARRIED OUT IN FEBRUARY 2023
Dismantling of existing structures and clearing of the territory - 100%
Temporary water supply (well) – 100%
Construction of temporary roads –100%
Tower crane installation – 100%
Earthworks – 50% (the excavation for the first floor is being carried out)
launch complex);
Installation of communication pipes under the foundation slab –50%;
Crushed stone and concrete slab preparation –20%