GENERAL CONSTRUCTION WORKS TO BE CARRIED OUT IN DECEMBER 2024

Work being done in December:


House 1:

Section 1: Plastering work is being carried out on floors 4-5. Plumbing work on floors 4-5, installation of window structures on floors 5-6, electrical installation work on floors 5-7.


Section 2: masonry of walls on floors 6-7 is being carried out. Installation of roof waterproofing.


House 2: installation of the building frame above the 0 mark. installation of vertical waterproofing of the house.


House 3: installation of the building frame above the 0 mark. Installation of vertical waterproofing of the house.