GENERAL CONSTRUCTION WORKS TO BE CARRIED OUT IN AUGUST 2024

Work in progress as of early August:


Concreting of the 6-storey slab, 1 section;

Installation of vertical structures 6-storey 2 sections;

Masonry of external walls of the 1st floor, 1-2 sections;

Masonry of ventilation ducts on the 5th floor, section 1-2;

Installation of the SKD system, 5th floor, section 1-2;

Installation of horizontal waterproofing of the parking lot.