GENERAL CONSTRUCTION WORKS TO BE CARRIED OUT IN APRIL 2025
House 1
Completion of plastering work in the 2nd section on the 2nd floor
Completion of plumbing work on the 5th floor of the 2nd section
Completion of electrical installation work on the 5th floor of the 2nd section
Installation of floor screeds in the 1st section on the 3rd floor is in progress.
Installation of elevator equipment in the 1st section has been completed
Roofing work has been completed in the 2nd section
House 2
Installation of the 5th floor slab
The laying of external and internal walls and partitions on the 3rd floor continues
Electrical installation work is underway on the 1st floor.
Installation of ventilation ducts on the 4th floor
House 3
The installation of the 5th floor floor slab is in progress.
Ventilation duct installation on the 4th floor
Waterproofing and backfilling of foundation cavities completed
Parking
Completion of work on installing the ventilation system
Installation of a sprinkler fire extinguishing system has begun
Work has begun on the construction of a fire pump station