GENERAL CONSTRUCTION WORKS TO BE CARRIED OUT IN APRIL 2024

Work in progress as of early April:

Preparatory work – completed;

Installation of temporary roads - completed;

Tower crane installation - completed;

Earthworks - excavation of the pit for the first launch complex - completed;

Installation of communication pipes under the foundation slab - completed;

Crushed stone and concrete preparation of the slab of the 1st launch complex - completed;

Foundation plate 1 of the launch complex - completed;

Frame structures of 1 launch complex up to grade 0.000 - 40% (work is being carried out on the arrangement of vertical structures of section 2 of building No. 1)