GENERAL CONSTRUCTION WORK TO BE CARRIED OUT IN SEPTEMBER 2024

Works as of the beginning of September:

  • Earthworks (excavation for Building No. 1) – completed.

  • Earthworks (excavation for Building No. 2) – 20% completed.

  • Frame construction of phase 1 above 0.000 level – 90% completed (works on the slab installation for the 7th floor of section 1 and the monolithic frame for the 6th floor of section 2 of Building No. 1 are in progress).

  • Wall and partition masonry of phase 1 – 15% completed (works are ongoing on the 2nd floor of sections 1 and 2).

  • Installation of ventilation ducts and chimneys for Building No. 1 – 40% completed.

  • Vertical waterproofing of the parking lot for Building No. 1 – 40% completed.