GENERAL CONSTRUCTION WORK TO BE CARRIED OUT IN NOVEMBER 2024

Works as of the beginning of November:

Building No. 1:

  • The monolithic frame has been completed.

  • Wall masonry is in progress: 4th-5th floors of section 1 and 1st-2nd floors of section 2.

  • Roofing installation is underway.

  • Plumbing works, network installation, and plastering on the 2nd floor.

  • Electrical network installation.

Building No. 2:

  • Foundation slabs are being installed.

  • Tower crane installation is in progress.