GENERAL CONSTRUCTION WORK TO BE CARRIED OUT IN MAY 2024

Works performed as of the beginning of May:

Preparatory works – completed;

Arrangement of temporary roads - completed;

Tower crane installation - completed;

Installation of communication pipes under the foundation slab - completed;

Crushed stone and concrete preparation of slab 1 of the launch complex - completed;

Monolithic frame of 1 launch complex up to 0.000 - 70%;

Structures of the frame 1 of the launch complex up to 0.000 - 40% (works are being carried out on the arrangement of the vertical structures of section 2 of building №1);

Monolithic framework of 1 launch complex above grade 0.000-5%; (work is being carried out on the arrangement of the floor slab of the 1st floor of the first section and the slab of the basement floor of the 2nd section of building №1) .