GENERAL CONSTRUCTION WORK TO BE CARRIED OUT IN MARCH 2024
Preparatory works – 100%;
Arrangement of temporary roads -100%;
Tower crane installation -100%;
Earthworks - development of the pit for the first launch complex is underway - 70%;
Installation of communication pipes under the foundation slab -50%;
Crushed stone and concrete preparation of slab 1 of the launch complex - 40%;
Foundation slab 1 of the launch complex -45% (concreting of foundation slab 1 of section building 1 is completed);
Structures of the frame 1 of the launch complex up to 0.000 -10% (works are being carried out on the arrangement of the vertical structures of section 1 of building No. 1)