GENERAL CONSTRUCTION WORK TO BE CARRIED OUT IN JANUARY 2024

Temporary water supply (well) - 100%

Dismantling of existing structures and clearing the territory - 100%

Construction of temporary roads -100%

Preparatory work – 100% (temporary arrangement completed

fencing of the construction site, household trailers installed,

security posts, a washing post, and construction lighting was completed

site).

Tower crane foundation plate-100%

Earthworks - 30% (development of the pit for the first

launch complex)