GENERAL CONSTRUCTION WORK TO BE CARRIED OUT IN JANUARY 2024
Temporary water supply (well) - 100%
Dismantling of existing structures and clearing the territory - 100%
Construction of temporary roads -100%
Preparatory work – 100% (temporary arrangement completed
fencing of the construction site, household trailers installed,
security posts, a washing post, and construction lighting was completed
site).
Tower crane foundation plate-100%
Earthworks - 30% (development of the pit for the first
launch complex)