GENERAL CONSTRUCTION WORK TO BE CARRIED OUT IN FEBRUARY 2024
Dismantling of existing structures and clearing the territory - 100%
Temporary water supply (well) - 100%
Construction of temporary roads – 100%
Tower crane installation -100%
Earthworks - 50% (development of the pit for the first
launch complex);
Installation of communication pipes under the foundation slab – 50%;
Crushed stone and concrete slab preparation -20%