GENERAL CONSTRUCTION WORK TO BE CARRIED OUT IN APRIL 2024

Works performed as of the beginning of April:

Preparatory works – completed;

Arrangement of temporary roads - completed;

Tower crane installation - completed;

Earthworks - development of the pit for the first launch complex - completed;

Installation of communication pipes under the foundation slab - completed;

Crushed stone and concrete preparation of slab 1 of the launch complex - completed;

Foundation plate 1 of the launch complex - completed;

Structures of the frame 1 of the launch complex up to 0.000 - 40% (work is being carried out on the arrangement of the vertical structures of section 2 of building No. 1)